A data frame with 32 observations on the following 11 variables.
- cost
The capital cost of construction in millions of dollars
adjusted to 1976 base.
- date
The date on which the construction permit was issued. The
data are measured in years since January 1 1990 to the
nearest month.
- t1
The time between application for and issue of the
construction permit.
- t2
The time between issue of operating license and construction
permit.
- cap
The net capacity of the power plant (MWe).
- pr
A binary variable where `1' indicates the prior existence of
a LWR plant at the same site.
- ne
A binary variable where `1' indicates that the plant was
constructed in the north-east region of the U.S.A.
- ct
A binary variable where `1' indicates the use of a cooling
tower in the plant.
- bw
A binary variable where `1' indicates that the nuclear steam
supply system was manufactured by Babcock-Wilcox.
- cum.n
The cumulative number of power plants constructed by each
architect-engineer.
- pt
A binary variable where `1' indicates those plants with
partial turnkey guarantees.