Create a Gantt Chart representing the events in a completed simulation.
This event diagram is constructed using the completed event list
To change the number of events shown, provide an n
argument.
eventDiagram(sim, n, startDate, ...)# S4 method for simList,numeric,character
eventDiagram(sim, n, startDate, ...)
# S4 method for simList,missing,character
eventDiagram(sim, n, startDate, ...)
# S4 method for simList,missing,missing
eventDiagram(sim, n, startDate, ...)
A simList
object (typically corresponding to a
completed simulation).
The number of most recently completed events to plot.
A character representation of date in YYYY-MM-DD format.
Additional arguments passed to mermaid
.
Useful for specifying height
and width
.
Plots an event diagram as Gantt Chart, invisibly returning a mermaid
object.
Simulation time is presented on the x-axis, starting at date 'startDate'. Each module appears in a color-coded row, within which each event for that module is displayed corresponding to the sequence of events for that module. Note that only the start time of the event is meaningful is these figures: the width of the bar associated with a particular module's event DOES NOT correspond to an event's "duration".
Based on this StackOverflow answer: http://stackoverflow.com/a/29999300/1380598.